Check out 10 transportation projects in Frisco


Check out some transportation projects happening or scheduled to start in the Fresh.

Ongoing projects

1. Construction of Panther Creek Parkway

Project: Panther Creek Parkway will be created into a six-lane divided highway that spans the Dallas North Overpass to Preston Road.

Update: The project is under construction, according to city ​​capital improvement website.

  • Time frame: March 2024 – December 2025
  • Cost: 56.4 million dollars
  • Funding sources: Collin County, City of Frisco

2. Construction of Hillcrest Road

Project: The project will build a four-lane divided road from Panther Creek Parkway to PGA Parkway.

Update: The project is under construction and is headed for completion next year.

  • Time frame: March 2024-June 2025
  • Cost: $5.99 million
  • Funding source: the city of Frisco

3. Universal Parkway construction

Project: The project will create a new two-lane road from Dallas Parkway to Panther Creek Parkway in anticipation of Universal Kids Resort, which is expected to open in 2026.

Update: The project is under construction and is on track for completion at the end of this year.

  • Time frame: September 2023-December 2024
  • Cost: 12.94 million dollars
  • Funding source: the city of Frisco

Future projects

4. Custer Street Light Assembly

Project: The intersection at Custer Road and Gartner Road will see a new traffic light installed.

Update: The project is in the design phase. The design phase was expected to be completed by the end of the second quarter. Construction is expected to be completed by the end of the year.

  • Time frame: TBD-December 2024
  • Cost: 250,000 dollars
  • Funding source: the city of Frisco

5. Widening of Teel Parkway

Project: The project will stretch along Teel Parkway from Stafford Middle School to Olive Branch Drive. The project will widen the road from two lanes to four lanes, according to Frisco's capital improvement database.

Update: The project is in the planning stage.

  • Time frame: September 2025 – December 2026
  • Cost: 10 million dollars
  • Funding source: the city of Frisco

6. Coit Road at Charismatic Parkway light installation

Project: A new traffic signal will be added to the intersection at Coit Road and Charismatic Parkway, according to the city's capital improvement website.

Update: The project is in the design phase. The project was supposed to start construction at the end of June.

  • Time frame: TBD-December 2024
  • Cost: 250,000 dollars
  • Funding source: the city of Frisco

7. Installation of Main Street traffic lights

Project: A new traffic light will be added to the intersection at Main Street and Kings Ridge Road.

Update: The project is in the design phase and should be completed by the end of this year, according to the city's capital improvement website.

  • Time frame: TBD-December 2024
  • Cost: 250,000 dollars
  • Funding source: the city of Frisco

8. Frisco Roundabout Addition

Project: Several roundabouts will be added to Frisco Road at Technology Drive, Sports Village Road, All Stars Avenue and Research Drive.

Update: The project is still in its design phase and construction will begin later this year.

  • Time frame: December 2024-March 2026
  • Cost: 9 million dollars
  • Funding source: the city of Frisco

9. Construction of Meadow Hill Drive

Project: The project will reconstruct Meadow Hill Drive from North County Road to Rogers Road.

Update: The project has been placed on hold.

  • Time frame: TBD
  • Cost: 3.7 million dollars
  • Funding source: the city of Frisco

10. Construction of Frisco Road

Project: The project will build a four-lane divided road along Frisco Road from Cobb Hill Drive to Panther Creek Parkway.

Update: The project has been placed on hold, according to the city's capital improvement website.

  • Time frame: TBD
  • Cost: 8.71 million dollars
  • Funding source: the city of Frisco